Original EA Amendment

6.4.3. Impact Assessment

The proposed operations at Mount Morgan will result in the reduction of contaminant sources via the

excavation and placement of historical ARD generating mine waste and redeposition into the Sandstone

Gully TSF, the OCP and (if approved) the Upper Mundic Gully TSF and rehabilitation of operational

areas utilised by Heritage Minerals in accordance with the State Rehabilitation Plan (Unger et al, 2003)

and Phase 2 Agreement leaving the site in an improved condition.

Potential impacts on land from construction and operation of the Upper Mundic Gully TSF are unlikely

given the significant existing disturbance within the area associated with the Western Dump placement

and previous construction and operation of the water diversion tunnel. The construction of the Upper

Mundic Gully TSF will likely improve impacts to land as the currently exposed face of the Western Dump

will be sealed.

The risk of exacerbating onsite and offsite contamination will also be minimised through the

implementation of rigid TSF design, surface water controls associated with the TSF inspection regimes

and groundwater monitoring. Through implementation of rehabilitation measures the Upper Mundic

Gully TSF will achieve a final landform that is:

Safe to humans and wildlife;

Non-polluting;

Stable; and

• Able to sustain an appropriate land use after rehabilitation or restoration.

6.4.4. Management Practices

The primary objective for Project land management will be to facilitate progressive tailing reprocessing

and Mount Morgan Mine rehabilitation and remediation in accordance with the State’s Rehabilitation

Plan (Unger et al, 2003) and Phase 2 Agreement.

The major waste stream generated from the proposed amendments are mineral wastes in the form of

tailings that have been processed to remove contaminant mass. Permanently storing tailings in a

bespoke managed TSF is considered best practice and is a better environmental outcome than the

current setting whereby latent tailings (and waste rock) provides a source of contamination that

continues to impact the environmental values of receptors, particularly the Dee River.

In addition to these, the Heritage Minerals Soil and Hazardous Substances Procedures provide

standard controls for various Project activities including chemical and hazardous material storage, spill

response and soil management.

6.5. Noise and Vibration

In preparing this application, consideration has been given to guideline ESR/2015/1838 – Application

requirements for activities with noise impacts (DETSI, 2024e). DETSI is required to assess the

application against the requirements stated in the Environmental Protection Act 1994 , EP Regulation

155

Wulguru Technical Services Pty Ltd – Supporting Information to Amend an Environmental Authority

Powered by