Table 10. Proposed Table H2 Replacement
Consequence Category
Maximum Surface area (ha)
Maximum volume (m 3 )
Purpose of Regulated Structure
Name of Regulated Structure
Sandstone Gully Tailings Storage Facility Upper Mundic Gully Tailings Storage Facility
High
49.2
11,532,416
Storage of Cyanide Tailings
Significant
43.4
9,240,000
Storage of Tailings
Justification for changes described in Table 10 are as follows:
• The existing values in Table H3 relating to spillway, DSA and MRL do not reflect the ‘High’
consequence category for Dam Break (and ‘Low’ for Overtopping and Seepage);
• Changes to Spillway are derived from Table 6 from the DETSI Manual for assessing
consequence categories and hydraulic performance of structures;
• Changes to DSA are derived from Table 3 of ANCOLD requirements; and
• Changes to mandatory reporting level are derived from Table 5 from the DETSI Manual for
assessing consequence categories and hydraulic performance of structures.
Table 11. Proposed Table H3 Replacement
Name of Regulated Structure
Spillway
Design Storage Allowance
Mandatory Reporting Level
Sandstone Gully Tailings Storage Facility
1:20 AEP
Peak discharge from a 0.001 AEP storm of critical time of concentration on the total
1:10 AEP 72-hour ESS
1:100,000 AEP + Wave run-up allowance for 1:10 AEP wind
1:100 AEP 72-hour duration ESS
natural catchment with diversions inoperable
1:5 AEP Wet Season Water Storage DSA
2.3.3. Figures within the EA
Justification for amendments to Schedule I, Figure 1 include:
• Inclusion of the Upper Mundic Gully TSF to ensure consistency with Table A1; and
• Inclusion of the pipe corridor to ensure consistency with Table A1.
The proposed replacement Schedule 1, Figure 1 is provided in Figure 9.