LEGEND
210
EXISTING GROUND SURFACE AT 2 m CONTOUR INTERVALS
210
STAGE 1 EMBANKMENT DESIGN AT 2 m CONTOUR INTERVALS
210
STAGE 2 EMBANKMENT DESIGN AT 2 m CONTOUR INTERVALS
STAGE 1 INDICATIVE STORAGE FOOTPRINT
STAGE 2 INDICATIVE STORAGE FOOTPRINT
EXISTING STORMWATER DIVERSION TUNNEL
INDICATIVE LINER EXTENT
EXISTING MINESPOIL DUMP EXTENT
INDICATIVE STAGE 1 STORAGE FOOTPRINT RL 360 m
INDICATIVE EMBANKMENT FOOTPRINT STAGE 1 - REFER DRG 003
DAM 8
INDICATIVE STORAGE FOOTPRINT RL 390 m
7 384 000 N
7 384 000 N
TUNNEL OUTLET (NORTH EAST)
EXISTING STORMWATER DIVERSION TUNNEL REFER DRG 006
A 005
TUNNEL INLET (SOUTH WEST)
STAGE 2 EMBANKMENT REFER DRG 004
LINING REQUIREMENTS AND EXTENTS TO BE CONFIRMED'
400
7 383 500 N
7 383 500 N
OPEN CUT PIT
NOT FOR CONSTRUCTION PRELIMINARY
EXISTING MINESPOIL DUMP EXTENTS
0
100
200
1:5,000
METRES
CLIENT
PROJECT
HERITAGE MINERALS
MOUNT MORGAN GOLD PROJECT UPPER MUNDIC GULLY - TSF CONCEPT DESIGN
TITLE
CONSULTANT
BRISBANE OFFICE 900 ANN STREET FORTITUDE VALLEY, QLD 4006 AUSTRALIA [+61] (7) 3854 6200
GENERAL ARRANGEMENT PLAN
B 2025-07-04 PRELIMINARY - NOT FOR CONSTRUCTION
DT/DW
EN/TD
MJG
MJG
A 2024-08-26 DRAFT - FOR INFORMATION ONLY
DT/DW
EN/TD
MJG
MJG
DOCUMENT No. 019
2 6 of
FIGURE 002
PS2132478 PROJECT NO.
REV.
B
DESCRIPTION YYYY-MM-DD
PREPARED REVIEWED APPROVED DESIGNED
REV.
Powered by FlippingBook