Original EA Amendment

Requirement

Relevant Section(s)

(e) if the application relates to a new relevant

resource tenure for the authority that is an

exploration permit or GHG permit—state

The application does not relate to a new relevant

whether the applicant seeks an amended

resource tenure that is an exploration permit or

environmental authority that is subject to the

GHG permit

standard conditions for the relevant activity or

authority, to the extent it relates to the permit;

and

(f) include an assessment of the likely impact of

(i) Section 6 of this document describes the

the proposed amendment on the

potential impacts of the proposed amendment on

environmental values, including -

environmental values, including emissions or

(i)a description of the environmental values

release, risks and magnitude of potential impacts

likely to be affected by the proposed

and details of proposed prevention and/or

amendment; and

minimisation procedures.

(ii)details of emissions or releases likely to be

(ii) Details of the likely releases are described in

generated by the proposed amendment; and

Sections 4.3.2, 4.3.6, 4.3.7 and Section 6.

(iii)a description of the risk and likely

(iii) A standalone description of risk and likely

magnitude of impacts on the environmental

magnitude of impacts on environmental values is

values; and

provided in Section 2.4 whilst a full risk assessment

(iv)details of the management practices

is provided in Section 7.

proposed to be implemented to prevent or

(iv) Existing management practices are detailed in

minimise adverse impacts; and

Section 6.

(v)if a PRCP schedule does not apply for each

(v) As a PRCP schedule is not in place,

relevant activity—details of how the land the

rehabilitation aspects are discussed in Section

subject of the application will be rehabilitated

6.4.2.

after each relevant activity ends; and

(g) Include a description of the proposed

A description of waste management procedures

measures for minimising and managing waste

related to this amendment are discussed in Section

generated by amendments to the relevant

6.10 of this document. The Waste Management

activity; and

plan is provided in Appendix E.

There is no site management plan or environmental

(h) Include details of any site management plan or

protection order relating to the land subject to the

environmental protection order that relates to

application. The land subject to this application is

the land the subject of the application.

managed by the DNRMMRDD under the AMLP.

As a PRCP schedule is not in place, section 226AA of the EP Act is not applicable. No changes to the

authorised take of associated water are proposed therefore Section 227AA does not apply. This

application does not relate to an EA for a CSG activity, therefore Section 227 requirements for

amendment application – CSG activities are not applicable.

56

Wulguru Technical Services Pty Ltd – Supporting Information Report