Original EA Amendment

• Phase 1 (Month 0-11): Modelling of the construction phase including dewatering of Sandstone

Gully to OCP;

• Phase 2 (Month 12-51): Modelling of the period where the OCP functions as the TSF;

• Phase 3 (Month 52-73): Modelling of the period where the Upper Mundic Gully TSF functions

as the TSF; and

• Phase 4 (Month 74-94): Modelling of remaining five years where the Upper Mundic Gully TSF

functions as the TSF.

Results of the water balance modelling indicate that the newly proposed Upper Mundic Gully TSF shows

general seasonal increases through the wet season in Phases 1 and 2 (see Figure 24), assuming that

the tunnel to the Dam 8 is sealed. Once Upper Mundic Gully becomes the receiving TSF (from Phase

3 onwards), the base levels begin to rise with the tailings deposited, with only minor fluctuations in water

levels due to the reuse of the water being released form the deposited tailings. The results presented

in this figure also confirm that the TSF was not simulated to spill based on the maximum level as

simulated in this study, using the historical climatic data. The results presented for OCP water levels

(Figure 25) were assessed for the following key levels in OCP as specified by Heritage Minerals:

267.3 m AHD;

263.0 m AHD; and

• 259.3 m AHD to sustain a 1% AEP buffer volume.

Table 27 presents the simulated key water levels along with corresponding dates. All simulated dates

fall within Phase 2 except for the date associated with a relative level of 259.3m AHD in OCP, which

occurred during Phase 3. During Phase 3, late 2029 (UMG as TSF), OCP water levels were simulated

to continue dropping further at an increased rate. The spill level of the OCP is at 273.52 m AHD and

the simulations show that there is negligible spill risk as shown in Figure 25, due to the declining water

level.

Table 27. Simulated dates for OCP levels at various RLs

Relative Level (mAHD)

July Simulations

50 th

75 th

267.3

21/06/2026

05/10/2026

263

25/01/2028

16/10/2028

18/08/2029 1

18/11/2029 1

259.3

1 Phase 3

90

Wulguru Technical Services Pty Ltd – Supporting Information to Amend an Environmental Authority

Powered by