Mount Morgan Mine Upper Mundic Gully TSF EA Amendment

∕ ∕ ∕

Shepherd’s Gully Tailings Dam;

Magazine Dump; and Mullock Dumps K and Q.

Figure 8. Extract from PoO 2017 (AARC)

2.2

Amendment Justification

2.2.1 Justification for Proposed Amendment 1 Upper Mundic Gully TSF approval will facilitate a life of mine permanent tailings location to support Heritage Mineral’s remediation project. Although the Sandstone Gully TSF is approved as a mine feature in the EA, significantly more latent tailings are present within the footprint than was previously assumed. To enable the construction of Sandstone Gully TSF, removal of latent tailings must occur. However, due to the ground