Original EA Amendment

EA Condition

Action Program

(a) address the complaint including the use of appropriate dispute resolution if required; and (b) immediately implement noise abatement measures so that emissions of noise from the activity do not result in further environmental nuisance.

undertaken during the term of this PoO, it is anticipated that monitoring will not be required.

D5

The method of measurement and reporting of noise levels must comply with the

If requested by the administering authority noise monitoring will be undertaken as required. However, due to the minor nature of activities being undertaken during the term of this PoO, it is anticipated that monitoring will not be required. If requested by the administering authority, noise monitoring will be undertaken. However, due to the minor nature of activities being undertaken during the term of this PoO, it is anticipated that monitoring will not be required. No mining is proposed during the term of this PoO. Only minor activities will occur on site during the term of this PoO. These will include maintenance and environmental investigations. These activities will occur during daytime hours only. No environmental nuisance from vibration is anticipated. If a complaint is received, an investigation will be conducted. If requested by the administering authority, vibration monitoring will be undertaken. Given that the activities proposed during the term of this PoO are minor in nature, it is anticipated that monitoring will not be required.

latest edition of the administering authority's Noise Measurement Manual.

D6 The holder of this environmental authority must undertake background noise monitoring and submit the results to the administering authority, before any mining activity commences onsite.

Vibration nuisance D7

Subject to conditions D8 and D9 vibration from the mining activity must not cause

an environmental nuisance, at any sensitive or commercial place.

D8 When requested by the administering authority, vibration monitoring must be undertaken within a reasonable and practicable timeframe nominated by the administering authority to investigate any complaint (which is neither frivolous nor vexatious nor based on mistaken belief in the opinion of the authorised officer) of environmental nuisance at any sensitive or commercial place, and the results must be notified within fourteen (14) days to the administering authority following completion of monitoring. D9 If the environmental authority holder can provide evidence through monitoring that the limits defined in Table D3 — Vibration limits are not being exceeded then the holder is not in breach of condition D7. Monitoring must include: (a) location of the blast(s) within the mining area (including which bench level); (b) atmospheric conditions including temperature, relative humidity and wind speed and direction; and (c) Location dates and time of recording.

If requested by the administering authority, vibration monitoring will be undertaken. However, due to the minor activities being undertaken during the term of this PoO, it is anticipated that monitoring will not be required.

D10

If monitoring indicates exceedance of the relevant limits in Table D3 — Vibration

If requested by the administering authority, vibration monitoring will be undertaken. However, due to the minor

limits , then the environmental authority holder must:

25

Plan of Operations

March 2019

AARC Environmental Solutions Pty Ltd

E info@aarc.net.au

AARC.NET.AU

Powered by