Original EA Amendment

12 February 2020

20137096-009 Rev A

suppliers and Golders past experience. The estimates Class 4 costs for all the raises are summarised in Table 6 with detailed costing provided in APPENDIX D.

Table 6: Provisional Costing Summary (Class 4)

Option 1 Clay Amount (AUD)

Option 2 HDPE Amount (AUD)

No.

Description

1.

-

13,524,862 Note 1

Stage 1 - Starter embankment to RL 290 m

2.

5,083,800

Stage 2 to RL 300 m

5,533,050

3.

5,090,200

Stage 3 to RL 310 m

5,625,700

4.

5,245,430

Stage 4 to RL 320 m

5,848,930

5.

5,791,646

Stage 5 to RL 330 m

6,445,146

6.

4,732,092

Stage 6 to RL 335 m

5,260,692

Direct Costs – Stage 2 to 6

28,713,518

25,943,168

Project Estimate – Stage 1 to 6

64,850,275

59,898,275

Note 1: includes – Direct costs, Contractor, Owners cost, Base estimate and Project contingency

11.0 WAY FORWARD

The following at least will need to be done going forward with this design.

 Geotechnical investigation of the embankment footprint

 Sample and testing of waste rock for downstream shell

Geochemical

Geotechnical

Sourcing and testing of

Clays and soils for seal zone

Gravel for filter drain

Water balance modelling.