Mount Morgan Mine Upper Mundic Gully TSF EA Amendment

Table 2.2

Basis of Design

Description

Criteria

Unit Basis Value

Source

General

Existing ground combined surface: — Mount_Morgan_2007.dxf – site contours provided 13 April 2016 — Mt_morgan_1604_e10.poi – April 2016 site LiDAR provided 6 May 2016 Pre mine combined surface: — Pre_mining_surf.dat — Premine_Topo_Robertson_ Geoconsultant.DXF

Design survey

-

-

Heritage

Survey system

-

-

MGA94 Zone 56

Heritage

Survey datum

-

-

Australian Height Datum

Heritage

— Stage 1: Significant — Stage 2: High B — Stage 1: Low — Stage 2: Significant

Consequence Category ANCOLD

-

WSP [1]

Consequence Category DETSI

-

WSP [1]

TSF Embankment

Crest width

Light traffic

m 10

WSP

Batter slopes

Liner requirement

H:V 2.5:1

WSP

Embankment

Mine spoil

-

Zoned with upstream liner

WSP

Stage 1 – Crest elevation Stage 2 – Crest elevation

-

RL m 360

WSP

-

RL m 390

WSP

Tailings

Specific gravity of tailings

-

-

3.02

Heritage

Slurry solids content -

% 40

Heritage

Tailings average settled dry density

-

t/m³ 1.10

WSP

Tailings beach slope

-

% 0.5

Heritage

Water management

Minimum freeboard

-

m 1

WSP

Project No PS213278 Upper Mundic Gully - Tailings Management Plan Mount Morgan Gold Mine Heritage Minerals