Mine Feature
Rehabilitation
Final Land Use
Land Suitability Objective
Surface Exploration
Backfill exploration holes. Replace vegetation
Land management monitoring and maintenance of rehabilitated areas Land management monitoring and maintenance of rehabilitated areas
Roads
Reshape & rehabilitate
Lachlan’s Laydown
Reshape and rehabilitate
Class 4
Paterson’s Patch Craig’s Clod
Justification for the changes described in Table 10 are as follows: ∕ Inclusion of the Upper Mundic Gully TSF in Table H1 is required to provide central points of the regulated structure. Table 10. Proposed Table H1 Replacement
Regulated Structure
Central Points
Latitude (GDA 94)
Longitude (GDA 94)
Sandstone Gully Tailings Storage Facility
-23.64196
150.36510
Upper Mundic Gully Tailings Storage Facility
-23.62970
150.35353
Justification for changes described in Table 11 are as follows: ∕ Updating the maximum volume of Sandstone Gully TSF, as justified in Section 2.2.3; ∕ Removing reference to “Cyanide” as referencing “Tailings” is sufficient to the purposes of describing the regulated structure; and ∕ Inclusion of the Upper Mundic Gully TSF in Table H2 is required to authorise the consequence category, maximum surface area, maximum volume and purpose. Table 11. Proposed Table H2 Replacement
Name of Regulated Structure
Consequence Category
Maximum Surface area (ha)
Maximum volume (m 3 )
Purpose of Regulated Structure
Sandstone Gully Tailings Storage Facility Upper Mundic Gully Tailings Storage Facility
High
49.2
11,532,416
Storage of Cyanide Tailings
Significant
43.4
9,240,000
Storage of Tailings
Justification for changes described in Table 11 are as follows: ∕ The existing values in Table H3 relating to spillway, DSA and MRL do not reflect the ‘High’ consequence category for Dam Break (and ‘Low’ for Overtopping and Seepage);
Project number: 25B061
Page 32